Gilead project wind turbine appeal hearings begin

Gilead-hearing-day-oneCountylive.ca
Vehicles lined Demorestville’s main street as about 150 people travelled to the Sophiasburgh Town Hall for the first day of the Ostrander Point Environmental Review Tribunal, appealing the Ministry of the Environment approval of Gilead Power’s Ostrander Point industrial wind turbine project on the south shore of Prince Edward County.

Tribunal members Robert Wright and Heather Gibbs, lawyers for the Ministry of the Environment and Gilead Power were present along with parties to the appeal, the Prince Edward County Field Naturalists (PECFN) and the Alliance for the Protection of Prince Edward County (APPEC) and their legal representatives Eric Gillespie and Natalie Smith. Appeals are to be heard by PECFN, on grounds of harm to plants, animals or the natural environment; and the APPEC, on grounds of harm to human health.

“Gillespie’s opening statement outlined the reasons for the PECFN appeal of the project approval.  He noted Ostrander Point was recognized by local, provincial and national and international organizations as the worst site for wind turbines and that Ostrander Point is in the middle of the PEC South Shore Important Bird Area. “Because of that and also since this is the first multiple witness appeal on environmental grounds, the case is precedent setting,” said Cheryl Anderson, of the PECFN. Read article

1 thought on “Gilead project wind turbine appeal hearings begin

Leave a Reply