MOECC pulls support for two turbine locations in Clearview Township wind project

C-K airportWasaga Sun, Ian Adams
The Ministry of Environment and Climate Change is pulling its support for two turbine locations at the Fairview Wind project because of safety concerns at the Clearview Aerodrome.

In the MOECC’s closing argument to the environmental review tribunal reviewing the order approving the renewable energy application, it was determined the location of two turbines conflicted with the privately-owned Clearview Aerodrome.

Dr. Raymond Cox, a risk assessment expert in public safety, energy, and transport, as well as fluid dynamics and turbulence, testified during the hearing in June the two locations were without a five-rotor-diameter distance from the Clearview Aerodrome approach centreline.

“As it was the opinion of all expert witnesses, who opined on turbine wake … that there was an unacceptable safety risk where turbines are located within five rotor diameters from the centreline approach, the director can no longer support the locations of turbines 3 and 7 as currently approved,” wrote MOECC counsel Sylvia Davis and Andrea Huckins in their closing submission to the tribunal in August.

Clearview Aerodrome owner Kevin Elwood, who is one of the appellants to the MOECC’s  decision to approve WPD Canada’s renewable energy application, said it calls to question all eight turbines. Read article